Passive Foundation Ready to Receive SIPS Structure

Over the past few weeks our team has been busy preparing the passive foundation for our latest eco home build.


The basement is now ready and complete with block and beam cover and the remainder of the building(400m2) are prepared with a concreted sub base which will be finished with 200mm of thermal insulation and 65mm of reinforced fibre screed containing the underfloor heating system.


The SIP system will arrive on Wednesday and will take 3 weeks to complete.


Keep following as we will be posting daily pictures of the SIP build.